The following is an outline of the Contracting process as defined by ICANN, it is our goal to supplement this with actual contracting timelines and action items that are encountered by new TLD applicants. Information can be edited directly, or contact Andrew Merriam, andrew[at]tldesign.co

Steps & Timeline[edit | edit source]

  1. CIR (approx. 8 days)
    1. CIR Review
  2. Sign Registry Agreement
  3. Pre-Delegation Testing (approx. 6 weeks)
  4. Transition to Delegation (approx. 2 weeks)
  5. Delegation
  6. Registry Onboarding
    1. Sunrise (min. 60 days)

Contracting Information Request[edit | edit source]

Registry Agreement[edit | edit source]

  • See Summary and Examples on Signing Registry Agreement
  • ICANN suggested timeline: 7 days
  • Applicant timeline examples:

Post RA Provisioning[edit | edit source]

  • Contact Sheet - Establishes appropriate contacts for various contingencies.
  • Delegation Info - Can be established concurrently with PDT, but must be completed prior to Delegation. Includes information on Zone File Access; Bulk Thin Registration Data Access; Data Escrow Registry Reporting; URS; EPP; IDN Tables; SLA Monitoring.

Pre-Delegation Testing[edit | edit source]

  • See Pre-Delegation Testing for summary
  • ICANN suggested timeline: 2-3 weeks [1]
    • In prior documents, ICANN has broken this down as 2 weeks for testing, and an additional 2-3 weeks for reporting the PDT results. This seems to have been recently conflated and changed to a 6 week process, according to slides from ICANN 48 in Buenos Aires. [2]
  • Applicant timeline examples:
    • 21 days, Aug 5-Aug 26; DotShabaka. Yasmin Omer has explained that as the first applicant to go through PDT, their experience should not be taken as indicative of current ICANN processes.[3]
  • ICANN's Self-Test Tools

Transition to Delegation[edit | edit source]

  • ICANN suggested timeline: 2 weeks [2]
  • Applicant timeline examples:

Delegation[edit | edit source]

  • ICANN suggested timeline: within 30 business days [4]

Registry Onboarding[edit | edit source]

Sunrise Period[edit | edit source]

  • See Sunrise Period summary, (min. 60 days)
    • ICANN mandated timeline for Start Date Sunrise: 30 day notice period with a minimum of 30 days running [5]
    • ICANN mandated timeline for End Date Sunrise: no notice period, minimum of 60 days running [5]

Trademark Clearinghouse[edit | edit source]

Applicant Examples[edit | edit source]

References[edit | edit source]

  1. PDT FAQ v.2.2, ICANN
  2. 2.0 2.1 Papac, Krista. Registry Onboarding. PDF download
  3. Omer, Yasmin. dotShabaka Registry – Delegation & Beyond, ICANN 48 Presentation
  4. http://www.iana.org/reviews/kpis-gtld-delegation-201301 Consultation on gTLD Delegation and Redelegation Performance Standards
  5. 5.0 5.1 Murphy, Kevin. First Come, First-Served Sunrise Periods on the Cards. http://domainincite.com/14627-first-come-first-served-sunrise-periods-on-the-cards