New TLD contracting

Revision as of 23:42, 4 December 2013 by Elise (talk | contribs)

The following is an outline of the Contracting process as defined by ICANN, it is our goal to supplement this with actual contracting timelines and action items that are encountered by new TLD applicants. Information can be edited directly, or contact Andrew Merriam, andrew[at]tldesign.co

Steps & Timeline edit

  1. CIR (aprox. 8 days)
    1. CIR Review
  2. Sign Registry Agreement
  3. Pre-Delegation Testing (approx. 6 weeks)
  4. Transition to Delegation (approx. 2 weeks)
  5. Delegation
  6. Registry Onboarding

Contracting Information Request edit

Registry Agreement edit

Pre-Delegation Testing edit

Transition to Delegation edit

  • ICANN suggested timeline: 2 weeks
  • Applicant timeline examples:

Delegation edit

Registry Onboarding edit

Sunrise Period edit

  • See Sunrise Period summary
  • ICANN mandated timeline for Start Date Sunrise: 30 day notice period with a minimum of 30 days running [3]
  • ICANN mandated timeline for End Date Sunrise: no notice period, minimum of 60 days running [3]
  • Applicant timeline examples:

Trademark Clearinghouse edit

References edit

  1. PDT FAQ v.2.2, ICANN, http://newgtlds.icann.org/en/applicants/pdt#resources
  2. Omer, Yasmin. dotShabaka Registry – Delegation & Beyond, ICANN 48 Presentation
  3. 3.0 3.1 Murphy, Kevin. First Come, First-Served Sunrise Periods on the Cards. http://domainincite.com/14627-first-come-first-served-sunrise-periods-on-the-cards