The following is an outline of the Contracting process as defined by ICANN, it is our goal to supplement this with actual contracting timelines and action items that are encountered by new TLD applicants. Information can be edited directly, or contact [[Andrew Merriam]], andrew[at]tldesign.co | The following is an outline of the Contracting process as defined by ICANN, it is our goal to supplement this with actual contracting timelines and action items that are encountered by new TLD applicants. Information can be edited directly, or contact [[Andrew Merriam]], andrew[at]tldesign.co | ||
==Steps & Timeline== [[File:Registry Onboarding Timeline.png|thumb]] | ==Steps & Timeline== | ||
[[File:Registry Onboarding Timeline.png|thumb]] | |||
# [[CIR]] (approx. 8 days) | # [[CIR]] (approx. 8 days) | ||
## CIR Review | ## CIR Review |
Revision as of 00:16, 5 December 2013
The following is an outline of the Contracting process as defined by ICANN, it is our goal to supplement this with actual contracting timelines and action items that are encountered by new TLD applicants. Information can be edited directly, or contact Andrew Merriam, andrew[at]tldesign.co
Steps & Timeline[edit | edit source]
- CIR (approx. 8 days)
- CIR Review
- Sign Registry Agreement
- Pre-Delegation Testing (approx. 6 weeks)
- Transition to Delegation (approx. 2 weeks)
- Delegation
- Registry Onboarding
- Sunrise (min. 60 days)
Contracting Information Request[edit | edit source]
- See Contracting Information Request summary and example.
- ICANN's CIR Guide, with examples
- ICANN suggested timeline: 8 days
- Applicant timeline examples: _ days
Registry Agreement[edit | edit source]
- See Summary and Examples on Signing Registry Agreement
- ICANN suggested timeline: 7 days
- Applicant timeline examples:
Post RA Stuff[edit | edit source]
Pre-Delegation Testing[edit | edit source]
- See Pre-Delegation Testing for summary
- ICANN suggested timeline: 2-3 weeks [1]
- In prior documents, ICANN has broken this down as 2 weeks for testing, and an additional 2-3 weeks for reporting the PDT results. This seems to have been recently conflated and changed to a 6 week process, according to slides from ICANN 48 in Buenos Aires. [2]
- Applicant timeline examples:
- 21 days, Aug 5-Aug 26; DotShabaka. Yasmin Omer has explained that as the first applicant to go through PDT, their experience should not be taken as indicative of current ICANN processes.[3]
- Self-Test Tools are available at http://newgtlds.icann.org/en/applicants/pdt#resources
Transition to Delegation[edit | edit source]
- ICANN suggested timeline: 2 weeks
- Applicant timeline examples:
Delegation[edit | edit source]
Registry Onboarding[edit | edit source]
Sunrise Period[edit | edit source]
- See Sunrise Period summary, (min. 60 days)
Trademark Clearinghouse[edit | edit source]
References[edit | edit source]
- ↑ PDT FAQ v.2.2, ICANN, http://newgtlds.icann.org/en/applicants/pdt#resources
- ↑ Papac, Krista. Registry Onboarding. buenosaires48.icann.org/en/.../presentation-contracting-20nov13-en.pdf
- ↑ Omer, Yasmin. dotShabaka Registry – Delegation & Beyond, ICANN 48 Presentation
- ↑ 4.0 4.1 Murphy, Kevin. First Come, First-Served Sunrise Periods on the Cards. http://domainincite.com/14627-first-come-first-served-sunrise-periods-on-the-cards